Daily News
Project Acronym: LVEW | State: Completed | Expedition ID: 5024
▾▴ Toggle Texts
▾▴ Toggle Images
◱ Full Size Pics
⊻ Bottom of Page
... (?TBD)
- (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-08-06 ˇ
Change in Lithology, feet. We continue to recover mostly siliceous metapelite.
Change in Lithology, feet. We continue to recover mostly siliceous metapelite. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-08-05 ˇ
Sue Priest USGS Flagstaff arrived to coordinate outreach activities
Sue Priest (USGS,Flagstaff) arrived to coordinate outreach activities. U.S. Forest Service, personnel toured Monday. Interviews will be given to the Mammoth Times and a Regional TV, station Thursday. Regular site tours will begin on Tuesday, August 11. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-08-04 ˇ
At 1800 began tripping out to replace bit and
At 1800, began tripping out to replace bit and perform minor repairs to drilling tools. From, the geologists, the veins and fractures in the metamorphic rocks have become more open, and, the vein mineraogy is typical of the hydrothermal deposition in shallower rocks. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-08-03 ˇ
An additional 90 feet of core was recovered The
An additional 90 feet of core was recovered. The lithology remains the same; siliceous metapelite with graphite, calcite and pyrite. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-08-02 ˇ
Cored nearly 100 ft. today..........we're smokin'!
Cored nearly 100 ft. today..........we're smokin'! - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-08-01 ˇ
Much of the day was spent tripping back into the hole following the hydrofrac test. Coring resumed...
Much of the day was spent tripping back into the hole following the hydrofrac test. Coring resumed late afternoon. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-31 ˇ
A very high quality Borehole televiewer log was run
A very high quality Borehole televiewer log was run between 7178' and 7460' by Sandia personnel. An attempted hydrofracture was unsuccessful, even at pumping pressures approaching the lithostatic load. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-30 ˇ
Coring continued to 7460 feet at which point we
, , Coring continued to 7460 feet, at which point we began tripping out of the hole for a hydrofrac test by Mark Zoback and Steve Hickman - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-29 ˇ
The performance of DOSECC's Hybrid deep coring system continues
The performance of DOSECC's Hybrid deep coring system continues to improve. The rock is also becoming more cpompetent, resulting in a dramatic improvement of the coring rate. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-28 ˇ
The ""kinks"" continue to be worked out of the system, and we continue to recover core.
The ""kinks"" continue to be worked out of the system, and we continue to recover core. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-27 ˇ
After a slow beginning the coring project is back
After a slow beginning, the coring project is back on track and the drilling is proceeding rapidly., The final adjustments to the Drilling Information System are nearly complete. We look forward to, a productive 2 months of drilling. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-26 ˇ
BOP test was successfully completed cement in the casing
BOP test was successfully completed, cement in the casing was cored out. A shoe test will be performed, and coring should resume later today. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-25 ˇ
As of 1230, BOP tests continue. We do not expect to begin coring before tomorrow morning.
As of 1230, BOP tests continue. We do not expect to begin coring before tomorrow morning. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-23 ˇ
stack The DOSECC hybrid coring unit is being put
stack. The DOSECC hybrid coring unit is being put together with the Tonto mud system,, and we should start BOP testing this afternoon or early this, evening. The cement (30 feet or so) in the pipe and a few feet of the, formation will be cored, then a shoe test will be conducted. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-22 ˇ
The casing has been cemented in Next pipe will
The casing has been cemented in. Next pipe will be stretched to accomodate thermal expansion and the Blow Out Preventor (BOP) will be assembled and tested. We expect coring to begin by the weekend. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-20 ˇ
The ODP pipe that was standing in the derrick
The ODP pipe that was standing in the derrick last night, circulated out all the glop, and laid it down. Running the ""bushing string"" into the well and cementing it back up into the 13 3/8"" casing sometime tonight. - (inserted: 04.11.2022 12:50)
Long Valley LVEW: 1998-07-15 ˇ
The preparation of the drilling equipment started today
The preparation of the drilling equipment started today