Daily News from OODP Drillsites
Sultanate of Oman, 2018
▾▴ Toggle Texts
▾▴ Toggle Images
◱ Full Size Pics
⊻ Bottom of Page
... (?TBD)
- (inserted: 06.03.2018 01:00)
Oman: 2018-03-06 ˇ
The French geophysical logging team members have arrived and are
The French geophysical logging team members have arrived and are preparing to log the new boreholes - (inserted: 28.02.2018 01:00)
Oman: 2018-02-28 ˇ
Coring is complete! Four months, 1700 m drilled, 100% recovery.
Coring is complete! Four months, 1700 m drilled, 100% recovery. Bringing the total OmanDP core length to 3200 m - (inserted: 27.02.2018 01:00)
Oman: 2018-02-27 ˇ
We enjoyed our last day with Maqbool and Said and
We enjoyed our last day with Maqbool and Said and were sad to see our final trainees leave site. - (inserted: 26.02.2018 01:00)
Oman: 2018-02-26 ˇ
30 m to go at BA4A and surface casing cemented
30 m to go at BA4A and surface casing cemented at BA1D! - (inserted: 25.02.2018 01:00)
Oman: 2018-02-25 ˇ
We are nearing the end of the final cored hole
We are nearing the end of the final cored hole - hopefully the weather will hold out for us! - (inserted: 24.02.2018 01:00)
Oman: 2018-02-24 ˇ
Today Chief Scientist Peter Kelemen hosted visitors from GSO and
Today Chief Scientist Peter Kelemen hosted visitors from GSO and the US Embassy at BA4A - (inserted: 22.02.2018 01:00)
Oman: 2018-02-22 ˇ
A great end to the week - we reached 200m
A great end to the week - we reached 200m at BA4A and BA1D rotary is ready to start tomorrow. - (inserted: 21.02.2018 01:00)
Oman: 2018-02-21 ˇ
A change of drill bit this afternoon gave us a ...
A change of drill bit this afternoon gave us a little time to catch up and relax. We expect to reach 200m tomorrow. Meawhile the rotary hole at BA1C is complete to 400m today - (inserted: 20.02.2018 01:00)
Oman: 2018-02-20 ˇ
Another long day with 39 m cored - we are
Another long day with 39 m cored - we are halfway through BA4A! - (inserted: 18.02.2018 01:00)
Oman: 2018-02-18 ˇ
A whopping 39 m advance today! Total depth is 77.7m
A whopping 39 m advance today! Total depth is 77.7m tonight - (inserted: 17.02.2018 01:00)
Oman: 2018-02-17 ˇ
The casing has been extended and we were able to
The casing has been extended and we were able to recover more core now that circulating fluid return is restored. - (inserted: 15.02.2018 01:00)
Oman: 2018-02-15 ˇ
some beautiful cores this morning including a pegmatitic gabbro dyke
some beautiful cores this morning including a pegmatitic gabbro dyke > 1m thick - (inserted: 14.02.2018 01:00)
Oman: 2018-02-14 ˇ
We made a great start at BA4A with spud in
We made a great start at BA4A with spud in at 09:51 and 23.70 m drilled, 5.70 m cased! - (inserted: 13.02.2018 01:00)
Oman: 2018-02-13 ˇ
Today we completed the core description at BA1B and moved
Today we completed the core description at BA1B and moved our logging tent to final coring site BA4! - (inserted: 12.02.2018 01:00)
Oman: 2018-02-12 ˇ
BA1B is complete at 401.7m depth!
BA1B is complete at 401.7m depth! - (inserted: 11.02.2018 01:00)
Oman: 2018-02-11 ˇ
BA1C passed 200 m and BA1B passed 380 m today
BA1C passed 200 m and BA1B passed 380 m today - good progress at both sites! - (inserted: 10.02.2018 01:00)
Oman: 2018-02-10 ˇ
Many staff on site today as we overlap for handover
Many staff on site today as we overlap for handover from members of both the microbiology and geology teams - (inserted: 08.02.2018 01:00)
Oman: 2018-02-08 ˇ
We found some interesting textures and alteration in today's peridotite
We found some interesting textures and alteration in today's peridotite cores - (inserted: 07.02.2018 01:00)
Oman: 2018-02-07 ˇ
:) We passed 300 m at BA1B and 66m at
:) We passed 300 m at BA1B and 66m at BA1C today!