Daily News
Project Acronym: KOYNA | State: Post Moratorium | Expedition ID: 5058
▾▴ Toggle Texts
▾▴ Toggle Images
◱ Full Size Pics
⊻ Bottom of Page
... (?TBD)
- (inserted: 28.06.2017 02:00)
Koyna: 2017-06-28 ˇ
Completed well head fitting and tested at 4000 psi. Christmas
Completed well head fitting and tested at 4000 psi. Christmas tree has been placed. - (inserted: 25.06.2017 02:00)
Koyna: 2017-06-25 ˇ
Successfully completed cementation job.
Successfully completed cementation job. - (inserted: 24.06.2017 02:00)
Koyna: 2017-06-24 ˇ
Successfully completed 5 1/2" casing lowering.
Successfully completed 5 1/2" casing lowering. - (inserted: 23.06.2017 02:00)
Koyna: 2017-06-23 ˇ
Completed pull out. Started lowering 5 ½” casing. Float shoe
Completed pull out. Started lowering 5 ½” casing. Float shoe is placed at 3012 m. - (inserted: 22.06.2017 02:00)
Koyna: 2017-06-22 ˇ
Started R/I before lowering 5 ½” casing.
Started R/I before lowering 5 ½” casing. Completed R/I and established circulation for 2 hours. Started pull out. - (inserted: 21.06.2017 02:00)
Koyna: 2017-06-21 ˇ
Started R/I before lowering 5 ½” casing.
Started R/I before lowering 5 ½” casing. Completed R/I and established circulation for 2 hours. Started pull out. - (inserted: 20.06.2017 02:00)
Koyna: 2017-06-20 ˇ
Geophysical logging is in progress.
Geophysical logging is in progress. - (inserted: 19.06.2017 02:00)
Koyna: 2017-06-19 ˇ
Geophysical logging is in progress.
Geophysical logging is in progress. - (inserted: 18.06.2017 02:00)
Koyna: 2017-06-18 ˇ
Hydrofrac tests were conducted in the granitic basement beneath the
Hydrofrac tests were conducted in the granitic basement beneath the deccan traps in the Koyna region. - (inserted: 16.06.2017 02:00)
Koyna: 2017-06-16 ˇ
Geophysical logging is in progress.
Geophysical logging is in progress. - (inserted: 15.06.2017 02:00)
Koyna: 2017-06-15 ˇ
In the picture Gerd Klee and Florian Seebald form M/s.
In the picture Gerd Klee and Florian Seebald form M/s. Mesy Solex experts providing training to BGRL scientists. - (inserted: 12.06.2017 02:00)
Koyna: 2017-06-12 ˇ
Downhole logging sondes and the logging truck reach KFD1 drill
Downhole logging sondes and the logging truck reach KFD1 drill site. - (inserted: 11.06.2017 02:00)
Koyna: 2017-06-11 ˇ
Finally, we reached the target depth i.e., 3014 m. With ...
Finally, we reached the target depth i.e., 3014 m. With this drilling of first 3km pilot borehole in Koyna got completed. Necessary arrangements are in progress for the geophysical logging. Pull out is in progress. - (inserted: 09.06.2017 02:00)
Koyna: 2017-06-09 ˇ
R/I completed. Air hammer drilling started from 2913 m.
R/I completed. Air hammer drilling started from 2913 m. - (inserted: 07.06.2017 02:00)
Koyna: 2017-06-07 ˇ
Core bit and outer core barrel.
Core bit and outer core barrel. - (inserted: 06.06.2017 02:00)
Koyna: 2017-06-06 ˇ
Troubleshooting of hydraulic feed pump got completed.
Troubleshooting of hydraulic feed pump got completed. Resume R/I from 2870 to 2912 m. Short trip of 200 m pull out and R/I has been made to check the stability of the borehole. Coring started from 2912 m. - (inserted: 04.06.2017 02:00)
Koyna: 2017-06-04 ˇ
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation of mud is continued in the borehole. - (inserted: 03.06.2017 02:00)
Koyna: 2017-06-03 ˇ
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation of mud is continued in the borehole. - (inserted: 01.06.2017 02:00)
Koyna: 2017-06-01 ˇ
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation of mud is continued in the borehole. - (inserted: 31.05.2017 02:00)
Koyna: 2017-05-31 ˇ
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation ...
Troubleshooting of hydraulic feed pump is in progress. Meanwhile circulation of mud is continued in the borehole. Rain continues through most of the day.