(inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-08 ˇ
We fond more Worm.ChinesdHacker-2 virus in our LAN and its virus was killed.
We fond more Worm.ChinesdHacker-2 virus in our LAN and its virus was killed. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-07 ˇ
The footage of today was 9.6m, the highest since MH-2C coring.
The footage of today was 9.6m, the highest since MH-2C coring. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-06 ˇ
The core drilling bit was dull and the footage of coring today was 6.75m.
The core drilling bit was dull and the footage of coring today was 6.75m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-05 ˇ
Coring of MH-2C runs 23 went on well and we got much footage today.
Coring of MH-2C runs 23 went on well and we got much footage today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-04 ˇ
Mr Li Xueyong the vice minister of ministry of
Mr. Li Xueyong, the vice minister of ministry of science and technology, visited the drill site accompanied by director Wang Da. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-03 ˇ
Longing was hindered at the depth of 3678 m.
Longing was hindered at the depth of 3678 m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-02 ˇ
Binary file (standard input) matches
Binary file (standard input) matches (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-06-01 ˇ
The new core drilling bits were transported to drill site in the afternoon.
The new core drilling bits were transported to drill site in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-31 ˇ
All engineers had held a meeting to discuss how to longing in this morning.
All engineers had held a meeting to discuss how to longing in this morning. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-30 ˇ
We acquired nearly 9 m cores from the borehole of MH-2C today for a final depth of 3752.39m.
We acquired nearly 9 m cores from the borehole of MH-2C today for a final depth of 3752.39m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-29 ˇ
Mr. Yang Zhenkun, the member of datacenter left CCSD drill site.
Mr. Yang Zhenkun, the member of datacenter left CCSD drill site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-28 ˇ
It was complex in deep hole; the footage of today was very low.
It was complex in deep hole; the footage of today was very low. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-27 ˇ
We acquired nearly 7 m cores from the borehole of MH-2C today.
We acquired nearly 7 m cores from the borehole of MH-2C today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-26 ˇ
A piece of strange core was taken out from the experimental borehole(PP4 )today.
A piece of strange core was taken out from the experimental borehole(PP4 )today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-25 ˇ
Six old teacher form HuaZhong normal university visited CCSD drill site.
Six old teacher form HuaZhong normal university visited CCSD drill site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-24 ˇ
The depth of coring borehole is 3712.55m. ;A logging was conducted today.
The depth of coring borehole is 3712.55m. ;A logging was conducted today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-23 ˇ
The program recorded in CCSD drill site has been shown CCTV-1 channel broadcast.
The program recorded in CCSD drill site has been shown CCTV-1 channel broadcast. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-22 ˇ
Some guests came to CCSD drill site and visited the geological museum and labs.
Some guests came to CCSD drill site and visited the geological museum and labs. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-21 ˇ
We begin to sort out the photos that we took in the CCTV gala yesterday.
We begin to sort out the photos that we took in the CCTV gala yesterday. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-20 ˇ
Today was the busiest but also the most joyful
Today was the busiest but also the most joyful day. Hundreds of professional actors and actresses, thousands of geo-staff and students from around China and nearly ten thousand local people came here to take part in a CCTV gala, which features the dedications of Chinese geologists and drillers. The gala will be normally played on CCTV Channel One on May 23. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-19 ˇ
Some students from China University of Geology and HeNan institute of education visited CCSD drill...
Some students from China University of Geology and HeNan institute of education visited CCSD drill site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-18 ˇ
Madam Xu Zhiqin and Professor Yang Jingsui etc arrived at drill-site in the afternoon.
Madam Xu Zhiqin and Professor Yang Jingsui etc arrived at drill-site in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-17 ˇ
We give the mast spray painting today.
We give the mast spray painting today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-16 ˇ
The stage will be built completely soon.
The stage will be built completely soon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-15 ˇ
Mr. Su Dechen, the master of datacenter came to CCSD drill site.
Mr. Su Dechen, the master of datacenter came to CCSD drill site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-14 ˇ
Mr.Wurulin, the vice-governor of Jiangsu province, visited drill-site today.
Mr.Wurulin, the vice-governor of Jiangsu province, visited drill-site today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-13 ˇ
We are Building a stage near the CCSD drill site, it will be used in the performance.
We are Building a stage near the CCSD drill site, it will be used in the performance. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-12 ˇ
Donghai telecom is installing some PHS Base Station near the CCSD drill site again.
Donghai telecom is installing some PHS Base Station near the CCSD drill site again. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-11 ˇ
We acquired nearly 8 m cores from the borehole of MH-2C today.
We acquired nearly 8 m cores from the borehole of MH-2C today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-10 ˇ
Binary file (standard input) matches
Binary file (standard input) matches (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-09 ˇ
Director Wang Da and some logging engineers came to CCSD drill site today.
Director Wang Da and some logging engineers came to CCSD drill site today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-08 ˇ
Binary file (standard input) matches
Binary file (standard input) matches (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-07 ˇ
Drilling out went on smoothly very much and the depth of MH-2C is 3624 m.
Drilling out went on smoothly very much and the depth of MH-2C is 3624 m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-06 ˇ
Drilling out was hindered at the depth of 3577 m.
Drilling out was hindered at the depth of 3577 m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-05 ˇ
Some exhibition boards about the CCSD project we had designed are all finished until today.
Some exhibition boards about the CCSD project we had designed are all finished until today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-04 ˇ
Director Wang Da left drill site for Beijing in the morning.
Director Wang Da left drill site for Beijing in the morning. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-03 ˇ
Some trucks carried away the drill pipes for enlarging borehole today.
Some trucks carried away the drill pipes for enlarging borehole today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-02 ˇ
CCSD project center obtain diploma of countrywide 5.1 Labor.
CCSD project center obtain diploma of countrywide 5.1 Labor. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-05-01 ˇ
Today is Labor Day. We have taken some photos for the 70101 drilling team today.
Today is Labor Day. We have taken some photos for the 70101 drilling team today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-30 ˇ
Running in hole with casing will be ended tomorrow morning.
Running in hole with casing will be ended tomorrow morning. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-29 ˇ
We begin to run in hole with casing today.
We begin to run in hole with casing today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-28 ˇ
We designed some exhibition boards about the CCSD project today.
We designed some exhibition boards about the CCSD project today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-27 ˇ
Some students from JinLin University visited CCSD drill site today.
Some students from JinLin University visited CCSD drill site today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-26 ˇ
Logging is still going on in the rain; it will be ended in the evening.
Logging is still going on in the rain; it will be ended in the evening. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-25 ˇ
We have acquired nearly 9 m cores from the experimental borehole today.
We have acquired nearly 9 m cores from the experimental borehole today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-24 ˇ
We have asked the cleaner of the Baojie Company to clean our office
We have asked the cleaner of the Baojie Company to clean our office (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-23 ˇ
Some guests form CCTV and local officials visited CCSD drill site today.
Some guests form CCTV and local officials visited CCSD drill site today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-22 ˇ
Logging was hindered at the depth of 3600 m. We are enlarging the borehole of MH-2C again.
Logging was hindered at the depth of 3600 m. We are enlarging the borehole of MH-2C again. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-21 ˇ
In the afternoon of April 21, the engineers held a meeting to discuss the logging and safety...
In the afternoon of April 21, the engineers held a meeting to discuss the logging and safety problems. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-20 ˇ
The morning meeting determined that the logging begins at eight tomorrow morning.
The morning meeting determined that the logging begins at eight tomorrow morning.