(inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-12 ˇ
It took a long time to trip in today.
It took a long time to trip in today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-11 ˇ
The hole advance of today slowed down to 30m.
The hole advance of today slowed down to 30m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-10 ˇ
Current depth is 1200m.
Current depth is 1200m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-09 ˇ
Some visitors come here.
Some visitors come here. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-08 ˇ
The life of the bit being used is approaching
The life of the bit being used is approaching to 100 hours, it is the longest life bit since enlarging borehole. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-07 ˇ
we take an advance of nearly 33m today, which is the best progress since enlarging the borehole.
we take an advance of nearly 33m today, which is the best progress since enlarging the borehole. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-06 ˇ
We changed a bit after tripping out.
We changed a bit after tripping out. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-05 ˇ
Everything is going on smoothly.
Everything is going on smoothly. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-04 ˇ
All the cuttings obtained since enlarging borehole are being sent out for mineral resource...
All the cuttings obtained since enlarging borehole are being sent out for mineral resource dectection. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-03 ˇ
Some colleagues' children come here to spend their summer vacation.
Some colleagues' children come here to spend their summer vacation. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-02 ˇ
Some officials from the seismic bureau of the Jiangsu province visited our dirll-site.
Some officials from the seismic bureau of the Jiangsu province visited our dirll-site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-07-01 ˇ
At about four o'clock this morning, we reached 1000m favorably.
At about four o'clock this morning, we reached 1000m favorably. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-30 ˇ
The working is going on smoothly.
The working is going on smoothly. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-29 ˇ
A day that production is better.
A day that production is better. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-28 ˇ
After one week's working geologists from petrophysical lab and
After one week's working, geologists from petrophysical lab and core logging lab have finished collecting samples from the core store-room. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-27 ˇ
We reached the depth of 934.92m today.
We reached the depth of 934.92m today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-26 ˇ
After serveral days' rain, we can see the sun finally,and some visitors come here.
After serveral days' rain, we can see the sun finally,and some visitors come here. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-25 ˇ
Today is a special day as the CCSD project
Today is a special day as the CCSD project started drilling on the same day in last year. In the past year, 2000 metre target depth of the pilot hole drilling was successfully finished and satisfactory research achievements were obtained. The work is keeping on running steadily and we hope we can make persistent efforts and make more achievement in future. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-24 ˇ
The hole advance of yesterday was nearly 31m this
The hole advance of yesterday was nearly 31m, this is the best day since enlarging hole. We changed a bit in the evening. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-23 ˇ
It is raining all the day, therefore, all the geologists have to work inside.
It is raining all the day, therefore, all the geologists have to work inside. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-22 ˇ
Mr Zhangwei our chief engineer held a meeting to
Mr. Zhangwei, our chief engineer, held a meeting to summarize the work done since we have enlarged the hole and arrange the things to do in the next step. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-21 ˇ
The experts conducted the drilling pipe crack detection before trip in.
The experts conducted the drilling pipe crack detection before trip in. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-20 ˇ
The hole advance of today is nearly 24m.
The hole advance of today is nearly 24m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-19 ˇ
The drill mud is normal now. Thanks for the good work of our mud expert Mr. Jia Jun.
The drill mud is normal now. Thanks for the good work of our mud expert Mr. Jia Jun. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-18 ˇ
The drill mud had not been very normal for
The drill mud had not been very normal for several weeks. The online analysis data of CO2, CH4 had been very high. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-17 ˇ
The hole advance of today slowed down to 11.15m. We reached a depth of 701.56m this morning.
The hole advance of today slowed down to 11.15m. We reached a depth of 701.56m this morning. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-16 ˇ
The hole advance of today is 30.27 m the
The hole advance of today is 30.27 m, the longest since spud. It is really a lucky day for drillers. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-15 ˇ
There was a heavy thunderstorm this morning. We had to turned off all computer servers.
There was a heavy thunderstorm this morning. We had to turned off all computer servers. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-14 ˇ
The chief geologist, Prof. Yang Jingsui arrived at CCSD drillsite today.
The chief geologist, Prof. Yang Jingsui arrived at CCSD drillsite today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-13 ˇ
Recently, the drillers have been busy for preparing the casing plans of next stage.
Recently, the drillers have been busy for preparing the casing plans of next stage. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-12 ˇ
About 2100 m of casings 273mm in diameter have
About 2100 m of casings (273mm in diameter) have been transported to CCSD drillsite this morning. These casings are produced by Chengdu Seamless Steel Pipe Co. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-11 ˇ
Several members came back after short vacation.
Several members came back after short vacation. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-10 ˇ
A new bit was used while the old one was ineffective.
A new bit was used while the old one was ineffective. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-09 ˇ
Two middle school students visited our drill-site after knowing of the CCSDP by Internet.
Two middle school students visited our drill-site after knowing of the CCSDP by Internet. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-08 ˇ
Everything is ok. And we changed a new bit.
Everything is ok. And we changed a new bit. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-07 ˇ
The current depth is 536.80m.
The current depth is 536.80m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-06 ˇ
Hydro-hammer test is being conducted.
Hydro-hammer test is being conducted. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-05 ˇ
It is the ripe time to wheat, so farmers start harvesting.
It is the ripe time to wheat, so farmers start harvesting. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-04 ˇ
Professor Liu Zhongguang left here after finishing his working.
Professor Liu Zhongguang left here after finishing his working. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-03 ˇ
Some experts came back to drilling site after several days of field geological investigation.
Some experts came back to drilling site after several days of field geological investigation. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-02 ˇ
We changed a new bit to open hole.
We changed a new bit to open hole. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-06-01 ˇ
A shock absorber is be added before trip in.
A shock absorber is be added before trip in. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-31 ˇ
The football matchs on The World Cup began today
The football matchs on The World Cup began today, some people watch TV at evening, rather than playing table tennis. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-29 ˇ
Everything is going on smoothly.
Everything is going on smoothly. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-28 ˇ
We past the examination of safety.
We past the examination of safety. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-27 ˇ
Some foreign friends visited our drill-site.
Some foreign friends visited our drill-site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-26 ˇ
madam Xu left here to Beijing today.
madam Xu left here to Beijing today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-25 ˇ
Liu Zhongguang, a professor from USA, came to our drill-site for a research today.
Liu Zhongguang, a professor from USA, came to our drill-site for a research today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-24 ˇ
Today,many middle school students came here to visit our drill-site.
Today,many middle school students came here to visit our drill-site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2002-05-23 ˇ
Today a famous academician Sun Shu came to visit
Today a famous academician Sun Shu came to visit our driling site and gave some important advice for our project running.