(inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-19 ˇ
The depth of today was 3600 m. Some logging engineers come to CCSD drill site in the afternoon.
The depth of today was 3600 m. Some logging engineers come to CCSD drill site in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-18 ˇ
Two guests from Beijing arrived CCSD drill site they
Two guests from Beijing arrived CCSD drill site, they look round the geological museum to make a design about it. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-17 ˇ
We began to test wire line coring system and
We began to test wire-line coring system and recovered nearly 1.6 m of core of experimental borehole first time. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-16 ˇ
Drilling was overpressure pumping at the depth of 3576 m,So we began to trip out today.
Drilling was overpressure pumping at the depth of 3576 m,So we began to trip out today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-15 ˇ
Some reporters from the third drilling company visited the
Some reporters from the third drilling company visited the CCSD drill site and collected some information of the CCSD project. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-14 ˇ
The travelling block was carried to CCSD drill site in the afternoon.
The travelling block was carried to CCSD drill site in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-13 ˇ
Today, we begin to scan the old cores.
Today, we begin to scan the old cores. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-12 ˇ
The hydraulic jar and new swivel were carried to drill site today.
The hydraulic jar and new swivel were carried to drill site today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-11 ˇ
The core scanner can be used normally. We took about two days to debug the software of cores...
The core scanner can be used normally. We took about two days to debug the software of cores scanner. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-10 ˇ
Some guests from National development and reform commission visited drill site.
Some guests from National development and reform commission visited drill site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-10 ˇ
Today we got much more footage, it reached 31.60m.
Today we got much more footage, it reached 31.60m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-09 ˇ
Mr. Su Dechen, the master of data center will come to CCSD drill site tomorrow morning.
Mr. Su Dechen, the master of data center will come to CCSD drill site tomorrow morning. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-08 ˇ
We begin to debug the software of cores scanner.
We begin to debug the software of cores scanner. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-07 ˇ
The manager of Tianjin Lilin Machinery Group Co., Ltd. visited drill site.
The manager of Tianjin Lilin Machinery Group Co., Ltd. visited drill site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-06 ˇ
An old man of 75 years old from local
An old man of 75 years old from local farmers visited drill site. He said he was very interested in CCSD project. Director Wang Da left drill site for Beijing today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-05 ˇ
The parts of devices of core scanner repaired will be carried to drill-site.
The parts of devices of core scanner repaired will be carried to drill-site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-04 ˇ
Some guests visited the drill-site today. We are enlarging the borehole of MH-2C.
Some guests visited the drill-site today. We are enlarging the borehole of MH-2C. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-02 ˇ
Sidetracking of MH-2C runs 2 was completed. The footage of today is 24.19m.
Sidetracking of MH-2C runs 2 was completed. The footage of today is 24.19m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-04-01 ˇ
Sidetracking of MH-2C runs 2 went on well and we got much footage today.
Sidetracking of MH-2C runs 2 went on well and we got much footage today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-31 ˇ
The engineers started to logging after sidetracking in the noon.
The engineers started to logging after sidetracking in the noon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-30 ˇ
We keep on sidetracking today and the footage is 4.30m.
We keep on sidetracking today and the footage is 4.30m. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-30 ˇ
We downloaded the windows security update files and burned into CD.
We downloaded the windows security update files and burned into CD. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-29 ˇ
Some logging engineers arrived at ccsd drill site in the afternoon.
Some logging engineers arrived at ccsd drill site in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-28 ˇ
We begin to sidetrack today.
We begin to sidetrack today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-27 ˇ
All engineers held a meeting to discuss how to resolve the sidetracking in this morning.
All engineers held a meeting to discuss how to resolve the sidetracking in this morning. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-26 ˇ
According to the cores taken out, quality of the plug back cementing is ok.
According to the cores taken out, quality of the plug back cementing is ok. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-25 ˇ
We began coring and check plug back cementing quality in the afternoon.
We began coring and check plug back cementing quality in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-24 ˇ
We feel happy that the borehole starts to spud in today and it will keep drilling as usual.
We feel happy that the borehole starts to spud in today and it will keep drilling as usual. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-24 ˇ
The chief engineer Mr. Zhang wei come back to CCSD drill-site.
The chief engineer Mr. Zhang wei come back to CCSD drill-site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-23 ˇ
We are preparing for sidetracking.
We are preparing for sidetracking. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-22 ˇ
70101 drilling team organized a basketball match by themselves in the afternoon.
70101 drilling team organized a basketball match by themselves in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-22 ˇ
We are preparing for sidetracking.
We are preparing for sidetracking. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-21 ˇ
Our community of the CCSD network was completed and uploaded to CCSD website.
Our community of the CCSD network was completed and uploaded to CCSD website. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-21 ˇ
We are preparing for sidetracking.
We are preparing for sidetracking. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-20 ˇ
The experimental borehole near the CCSD drill site spudded in today.
The experimental borehole near the CCSD drill site spudded in today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-19 ˇ
We begin to make the community of the CCSD network. No footage today, we are preparing for...
We begin to make the community of the CCSD network. No footage today, we are preparing for sidetracking. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-18 ˇ
No footage today, we are preparing for sidetracking.
No footage today, we are preparing for sidetracking. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-17 ˇ
It is very cold today the temperature drops to
It is very cold today, the temperature drops to 10 degrees Centigrade , but some visitors still come to CCSD drill sit. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-16 ˇ
We vent the mud polluted by the cement in the afternoon.
We vent the mud polluted by the cement in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-15 ˇ
It took about two hours to plug back cementing
It took about two hours to plug back cementing in the morning. Toady, Some members of microbe lab arrived at CCSD drill site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-14 ˇ
No footage today, we are waiting for plug-back cementing.
No footage today, we are waiting for plug-back cementing. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-13 ˇ
Binary file (standard input) matches
Binary file (standard input) matches (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-12 ˇ
The wire-line coring system was carried to CCSD drill site in the afternoon.
The wire-line coring system was carried to CCSD drill site in the afternoon. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-11 ˇ
Today,some engineers came back again to check all the across voltage protectors in drill-site.
Today,some engineers came back again to check all the across voltage protectors in drill-site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-10 ˇ
Today,Some new casing centralizers were transported to drill-site.
Today,Some new casing centralizers were transported to drill-site. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-09 ˇ
These practice students and their teacher ended their practice
These practice students and their teacher ended their practice and left here for Wuhan in the afternoon. Have a good trip. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-08 ˇ
About ten guests visited the CCSD drill-site today.
About ten guests visited the CCSD drill-site today. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-07 ˇ
A teacher from China University of Geology Wuhan showed
A teacher from China University of Geology (Wuhan) showed a lesson of management to members of CCSD in the morning. (inserted: 30.09.2022 17:41)CCSDP/Donghai: 2004-03-06 ˇ
There was something wrong with a computer. We took a long time to solve this problem.
There was something wrong with a computer. We took a long time to solve this problem.