As of the present date, we have finalized shipping arrangements ...
https://www.icdp-online.org/fileadmin/icdp/projects/data//hsdp//2003_03_14/IOD_DESC.txt

As of the present date, we have finalized shipping arrangements and most of the drilling equipment is currently in transit to Tacoma, Washington. The scheduled date of departure from Tacoma is 3/24 with arrival in Hilo on 4/9. Bruce Howell and the rig-up crew will arrive on 4/8 and will finalize the site design and be ready to begin rig-up on 4/10. Between now and 4/9, the Hawaii crew we will be completing as much of the site clearing and set-up as we can before the rig arrives.