Daily News
Project Acronym: HSDP | State: Completed | Expedition ID: 5027
ins.: 2003-03-21 01:00, 23 yrs ago

Category:
Hawaii_

hawaii: 2003-03-21
The rig and ~25 truckloads of hardware were successfully transported ...

The rig and ~25 truckloads of hardware were successfully transported to Tacoma, WA this week and are waiting to be loaded onto the barge (see photos). The barge is scheduled to leave late next week and we are planning to receive it here in Hilo on April 9. Offloading is scheduled for April 10 with trucking directly to the site from the barge. Progress is being made at the site to ready it for starting up operations. We will have a temporary office set up in about 10 days - and will begin the dozer work for placing the water tanks and mud tanks next week. Pray for good weather coming across the Pacific ....