Project Acronym: IDDP-2 | State: Completed | Expedition ID: 5029

ins.: 2016-09-22 02:00, 9 yrs ago
By: Scientists
Category: IDDP-2
IDDP-2

IDDP: 2016-09-22

A Kuster K-10 log was run on the 21st of ...
IDDP-2 drill site (Source Gudmundur ?mar Friddleifsson)

A Kuster K-10 log was run on the 21st of September and completed at 09:30. Subsequently 20 l/s were pumped on the well from 11:00 to 11:25 when cementing preparations were completed, but cementing commenced at 11:35. Cementing was at 2969 m depth (118,3 m of fibre pipes). Following the logging the rig crew used the cement string to find the top of cement, which appeared to be at 2960 m. 15 l/s were pumped on the well, which appeared not to show any losses. Therefore, it was concluded that the cement plugging had been successful.