Project Acronym: IDDP-2 | State: Completed | Expedition ID: 5029

ins.: 2016-10-04 02:00, 9 yrs ago
By: Scientists
Category: IDDP-2
IDDP-2

IDDP: 2016-10-04

The well was circulated for a good hour yesterday after ...
Drill rig on the IDDP-2 well in the background. On the left is the steam separation house of the Reykjanes power plant. (Source: Gudmundur Omar Fridleifsson)

The well was circulated for a good hour yesterday after the drill string had been pulled out, with a total circulation loss . Temperature, pressure and spinner logging was carried out, showing a new loss zone at ~3140m depth. Then the 2nd CORE barrel was run in hole from about noon yesterday. RIH was intermittently halted last night due to strong wind gusts. Core bit is expected to be at bottom this afternoon.