Project Acronym: IDDP-2 | State: Completed | Expedition ID: 5029

ins.: 2016-09-12 02:00, 9 yrs ago
By: Scientists
Category: IDDP-2
IDDP-2

IDDP: 2016-09-12

Cleaning of the well went well. Polymer and water were ...
Overview image of the IDDP2 drill site (Source: Gu?mundur ?mar Fri?leifsson).

Cleaning of the well went well. Polymer and water were used to clean out the bottomfill. Consequent losses were measured 4 L/s. The bit was then pulled into the casing and an hour later the bit was run down the whole to check the bottomfill which was none. Losses were 12 L/s. Consequently preparations for a cement job were executed and a temperature log was ordered to evaluate conditions at the bottom of the well for the cementing job.