Project Acronym: IDDP-2 | State: Completed | Expedition ID: 5029

ins.: 2016-12-07 01:00, 9 yrs ago
By: Scientists
Category: IDDP-2
IDDP-2

IDDP: 2016-12-07

Coring was terminated at 8:00 yesterday after coring from 4308.7 ...
Drill rig Thor at IDDP-2 drill site. (Source: Gudmundur Omar Fridleifsson)

Coring was terminated at 8:00 yesterday after coring from 4308.7 to 439.09 m. Subsequently the string was pulled out of hole pumping 13 L/s on the kill-line. The core barrel was at the rig floor at 20:45. Unfortunately, no core was recovered in core run 9. Afterwards a new core barrel was prepared and running into hole for core run 10 started at 23:30. The core barrel at 08:00 was at a depth of 3250 m.