Daily News
Project Acronym: HSDPD | State: Completed | Expedition ID: 5053
ins.: 2014-11-13 23:00; ( Age: 10 yrs )
Category:
HSPDP
HSPDP: 2014-11-14
The Chew Bahir crew is still powering through at the ...
The Chew Bahir crew is still powering through at the first site, currently down to ~210m with primarily lake clay and total recovery now up to ~85%. Drilling water is still a bit of an issue due to the volume being consumed and transit time to the source being ~5 hours roundtrip, but a second water trucks is on it's way and the hope is that this will allow about 20 hours of drilling per day.