Daily News
Project Acronym: GOE-DEEP | State: In Operation | Expedition ID: 5075
ins.: 2017-05-23 02:00, 8 yrs ago

Category:
DSEIS_

DSEIS: 2017-05-23
The LM 90 hydraulic rig has been bolted to the ...

The LM 90 hydraulic rig has been bolted to the concrete platform. The feed frame of the machine is now inclined with a plunge of -43.6 degree. The machine will be commissioned in the upcoming days. Dseis team is looking forward to start drilling very soon!
- Links:
- /fileadmin/icdp/projects/data/dseis/2017_05_23/DIS_OTHER.htm