Skip to main content

Daily News

Project Acronym: MALLIK | State: Completed | Expedition ID: 5026

ins.: 2022-10-21 18:29, 3 yrs ago
By: sql
Category: Mallik

MALLIK: 2002-01-31

Drilling proceeded relatively smoothly until the late evening when
Scientific freezer being deployed at -30C at the rig site. Also note the 1m long pressure vessels on the right of the freezer. Hopes are high for the hydrate coring! On the picture you see Scott Dallimore (GSC).

Drilling proceeded relatively smoothly until the late evening when progress slowed as, problems were encountered with the mud system. As with the observation wells this illustrates the difficulty in drilling warm permafrost. In the morning the hole had reached 572m., Scott Dallimore moved to the drill site and met with science team and operations staff and was debriefed by Tim Collett on his extensive field filing system., In Inuvik, progress continued on all fronts without any plumbing problems.