STAR: 2022-05-30
We completed the down hole work at site 5 today.
![](/fileadmin/icdp/projects/data/star/2022_05_30/IOD.jpg)
We completed the down hole work at site 5 today. On Saturday we installed the seismometer and pore pressure pipe infrastructure. We touched the grout at 112.5 m and then pulled the seismometer up to 111 m to align the screen with a fracture zone at 95 m. Today we sandpacked the screen section, put in a bentonite cap and cemented to 2 m below surface. The drillers also drilled and cased a 12 m hole for a broadband instrument.