Skip to main content
ins.: 2021-10-21 08:36; ( Age: 3 yrs )
By: Scientists
Category: STAR
STAR

STAR: 2021-10-20

Today we began drilling the second STAR borehole after
TSM02 after the rig was set up

Today, we began drilling the second STAR borehole after the drillers had moved on from TSM01 on Tuesday after a well-deserved break. They set surface casing to six meters and drilled to one meter. Work continues at TSM01 to complete the uphole installation. The strainmeter at TSM01 has been online since it was installed and recorded a 3.7 Mw approximately 70 km to the south east of the site on Monday.