Project Acronym: IDDP-1 | State: Completed | Expedition ID: 5029
ins.: 2004-12-21 01:00, 21 yrs ago

Category:
IDDP_

IDDP: 2004-12-21
The well was sidetracked out of its original RN-17 borehole ...

The well was sidetracked out of its original RN-17 borehole at 1995m but started to drift back into the RN-17 borehole again at a depth of 2001.4m drilling into the lower fish, where the drill-bit got stuck, following that a decision was made to abandon operations for now and continue in the new year with the drill-rig "Geysir". Operation to rig down Jötunn will continue but we from the IDDP team at Reykjanes take a brake from this page and wish you all Merry Christmas and a Happy New Year. Today is the shortest day of the year, just 6 hours 46 minutes of daylight. Seasons Greetings!!!