Project Acronym: IDDP-1 | State: Completed | Expedition ID: 5029

ins.: 2008-11-25 01:00, 17 yrs ago
By: Scientists
Category: IDDP_
IDDP_

IDDP: 2008-11-25

The casing was successfully cemented between 10:24-11:10 yesterday with 37 ...
The BOP?s are being removed to cut the casing and get ready for the next drilling stage, 18 5/8" intermediate casing 2 - down to approximately 800 m.

The casing was successfully cemented between 10:24-11:10 yesterday with 37 m3 of cement. The top cement job (2.2 m3) was completed at 12:30 o’clock. A temperature and CBL log run were finished by 06:10 o’clock early this morning. The casing was trimmed down at 11 o’clock, 24 hours after the cement job, and now preparations are underway for drilling stage 2.