Project Acronym: IDDP-1 | State: Completed | Expedition ID: 5029
ins.: 2009-05-21 02:00, 16 yrs ago

Category:
IDDP_

IDDP: 2009-05-21
First cement job commenced at 6:00 am this morning and ...

First cement job commenced at 6:00 am this morning and was completed at 7:41 am. 80 m3 of cement slurry was pumped through string. The slurry had an average density of 1.85 g/cm3. All 80 m3 of cement slurry had been pumped down by 7:20, and after that was pumped down 18 m3 of water to displace all cement out of string. Temperature and CBL log will be carried out late in the afternoon or evening to locate TOC behind casing.