IDDP: 2009-05-23
Yesterday preparations for the second stage of cementing of the ...

Yesterday preparations for the second stage of cementing of the anchor casing were in progress. At 15 pm temperature logging was carried out. Additional cement, transported from Reykjavik, came to the drill site late last night. Between 3 am and 6:20 am this morning the cementing was carried out. Totally 155 m3 of cement slurry was pumped into the annulus, 140 m3 with density of 1.85 g/cm3 and 15 m3 of 1.9 g/cm3. Temperature and CBL-loggings are planned in the afternoon.