IDDP: 2008-11-24

There was an obstruction in the lowermost part of the ...
View to the south of Krafla geothermal power station at noon Sunday, the 23rd of November.

There was an obstruction in the lowermost part of the hole and after several attempts the casing was set at 260.5 m depth (14.4 m from bottom). This was completed at 01:00 am early this morning. Preparations for cementing the casing are now in progress. The cement string has been run down hole and since 06:00 am and the hole has been rinsed for mud with water and soda. Cementing will commence, when the hole has been cooled sufficiently.