Project Acronym: IDDP-1 | State: Completed | Expedition ID: 5029

ins.: 2009-05-25 02:00, 16 yrs ago
By: Scientists
Category: IDDP_
IDDP_

IDDP: 2009-05-25

After the last cementing, May 23th, the cement was given ...
The Tyr staff working on the wellhead in the cellar. Tops of previous casings may be seen on the photo.

After the last cementing, May 23th, the cement was given time to harden for approximately 15 hrs. Then the top the casing was cut, at 15 pm yesterday. The BOP stack was removed. Preparation for installation of a new flange is in progress. This morning attempts to unscrew the casing stub is underway. Temperature and CBL-loggings were carried out last night, revealing that the top of the casing is well bound.