IDDP: 2009-05-24

Yesterday, temperature and CBL loggings were carried out between 13 ...
Logging specialist from Iceland Geosurvey handling the CBL-probe.

Yesterday, temperature and CBL loggings were carried out between 13 and 19:30 pm. The results indicate that TOC was at c. 100 m depth and that the anchor casing is well bound in general. An exception is an interval between 1415 and 1500 m depth, where CBL show little signs of cement bounding. At 23:30 pm the cementing of the anchor casing was finished. The uppermost part of the annulus was filled with cement, using 5.6 cubic meters of cement slurry. A CBL logging is planned in the afternoon.