Daily News
Project Acronym: IDDP-1 | State: Completed | Expedition ID: 5029
ins.: 2009-05-04 02:00, 16 yrs ago

Category:
IDDP_

IDDP: 2009-05-04
Yesterday at 13:00 pulling out of hole was finished and ...

Yesterday at 13:00 pulling out of hole was finished and preparations for a new set up of BHA started. At 22:00 the string had been run to 800 m depth. Early this morning the bit reached the top of the plug at 1905 m depth. The plug was drilled down to 1953 m, not showing much signs of hardening. Tha plan is to continue drilling into the plug, to ca. 2000 m depth, before further decisions are made.
- Links:
- /fileadmin/icdp/projects/data/iddp/2009_05_04/DIS_OTHER.htm