IDDP: 2017-01-06
Yesterday the rig crew started to prepare for cementing the ...

Yesterday the rig crew started to prepare for cementing the casing and from 22 to 22:35 in total 24 m3 of cement slurry (density: 1.92 g/cm3) was pumped down to cement the casing. This was followed by 25.06 m3 of water. The cement job was completed just before midnight. Waiting on cement is still ongoing.
- Links:
- /fileadmin/icdp/projects/data/iddp/2017_01_06/DIS_OTHER.htm