IDDP: 2016-12-29

POOH operations commenced again from 2117 m depth at 20:30 ...
Drill rig Thor at IDDP-2 drill site in the background middle of photo. (Source: Gudmundur Omar Fridleifsson)

POOH operations commenced again from 2117 m depth at 20:30 on December 28th. These had been terminated due to stormy conditions. Between 00:30 and 04:45 today the BHA, including the Weatherford logging tool, were broken off. Subsequently the crew started preparations for running in the liner which commenced about 07:00 this morning. At 09:00 some 15 pipes were in the hole. Weather conditions at rig site are bad.